Preliminary building inquiry and preliminary building permit
Before submitting a building application, the building owner can request information about the construction project from the competent authority by means of a preliminary building inquiry on individual questions that would have to be decided in the building permit procedure and which can be assessed independently.
A preliminary planning application is usually useful if, for example, it is unclear whether a plot of land can be built on at all under the applicable building planning law. A preliminary building inquiry can save financial expenses, as not all the documents required for a building permit are necessary. In addition, the builder receives certainty about the buildability of a plot of land at an early stage.
The preliminary ruling is valid for three years and is binding on the competent authority for this period, provided that the content of the preliminary decision does not fundamentally deviate. An extension of the preliminary ruling is possible upon request.
Who should I contact?
The responsibility lies with the district, the independent city, the large independent city and the municipality with building supervisory powers.
Responsible authorities
Emsbüren - Fachbereich III - Planen, Bauen, Umwelt, Liegenschaften und Brandschutz
Timetable
from 08:00 to 12:00
and 14:00 to 16:00
Tuesday:
from 08:00 to 12:00
Wednesday:
from 08:00 to 12:00
Thursday:
from 08:00 to 12:00
and 14:00 to 18:00
Friday:
from 08:00 to 12:00
Contact
- Emsbüren:
- Building encumbrances: Entry - in the register of building encumbrances
- Building permit issuance
- Building permit issuance in the simplified building permit procedure
- Development plan
- Land use plan
- Nature conservation area: Determination
- Planning approval
- Preliminary building inquiry and preliminary building permit
- Urban land-use planning
- Emsbüren:
- Building permit issuance
- Building permit issuance in the simplified building permit procedure
- Land use plan
- Planning approval
- Preliminary building inquiry and preliminary building permit
- Regional Planning, Regional Spatial Planning Programme (RROP)
- Spatial planning procedure, state planning assessment
- Urban land-use planning
- Emsbüren:
- Building encumbrances: Entry - in the register of building encumbrances
- Building permit issuance
- Building permit issuance in the simplified building permit procedure
- Development contributions
- Development plan
- Discharge of waste water into public sewage systems: permit
- Disturbance of street lighting: message
- Flood protection
- House number: Fixing
- Land use plan
- Landscape and green space plans
- Nature conservation area: Determination
- Planning approval
- Preliminary building inquiry and preliminary building permit
- Regional Planning, Regional Spatial Planning Programme (RROP)
- Residential plots municipal
- Spatial planning procedure, state planning assessment
- Urban land-use planning
Which documents are required?
The application for a preliminary decision must be submitted with the appropriate form and should contain a site plan or excerpt from the land map, a description of the project and building templates.
What are the fees?
Fees apply, please contact the relevant authority.
What deadlines do I have to pay attention to?
Deadlines may have to be observed. Please contact the competent authority.
Period of Validity: 3 Years