For each construction site where

  • the anticipated duration of the work exceeds 30 working days and on which more than 20 employees are working at the same time, or
  • the scope of the work is expected to exceed 500 person-days,

an advance notice containing at least the information specified in Annex I must be sent to the competent authority at least two weeks before the construction site is set up. The advance notice shall be visibly displayed on the construction site and adapted in the event of significant changes.

Process flow

Pursuant to § 4 BaustellV, the client or his appointed third party must check whether one of the conditions pursuant to § 2 para. 2 BaustellV is fulfilled. If so, the advance notice must be submitted to the competent authority in good time, visibly displayed at the construction site and adapted in the event of significant changes.

Competent authority

One of the ten State Trade Inspectorates in Lower Saxony

Requirements

At least two weeks before setting up a construction site where

  • the anticipated duration of the work exceeds 30 working days and on which more than 20 employees will be working at the same time, or
  • the scope of the work is expected to exceed 500 person-days.

Which documents are required?

Mandatory information according to Annex I BaustellV:

  • Location of the construction site,
  • name and address of the client,
  • type of construction project,
  • name and address of the third party responsible in place of the client,
  • name and address of the coordinator,
  • expected starting date and duration of the work,
  • the maximum number of persons expected to be employed on the site,
  • the number of employers and contractors without employees expected to work on the site,
  • indication of the employers and contractors without employees already selected.
  • Address of the responsible third party also with telephone, fax and e-mail if necessary
  • Indication of the coordinator separately according to planning phase and execution phase, in addition to the address also with telephone, fax and e-mail if necessary

What deadlines do I have to pay attention to?

The advance notice shall be submitted to the competent authority at least 2 weeks before the construction site is set up.

Appeal

Signature of the builder or third party responsible instead of the builder with place and date

What else should I know?

Rule of thumb: Advance notice is generally required if the construction activities require the deployment of at least 4 workers over a period of more than 6 months.

Section 7 (1) No. 1 BaustellV: It is a regulatory offence to intentionally or negligently fail to provide the competent authority with advance notice, or to do so correctly, completely or in good time.

When planning the execution of work on a construction project, in particular the division of work and the calculation of execution times, the general principles according to §4 of the Occupational Health and Safety Act must be observed.

The advance notice must be displayed visibly on the construction site and adapted in the event of significant changes.

Technically approved by

Lower Saxony Ministry of Social Affairs, Health and Equality

Professionally released on

21.10.2020

Author

The text was automatically translated based on the German content.

competent Bodies


Staatliches Gewerbeaufsichtsamt Osnabrück
Address: Johann-Domann-Straße 2 , 49080 Osnabrück
Timetable

Data protection information


Landkreis Emsland
Address: Ordeniederung 1 , 49716 Meppen
Timetable
Postal address: Post Office Box 15 62 , 49705 Meppen
Timetable
Telephone: 05931 44-0
Fax: 05931 44-3621
Transport Connection:
Station Haltestelle Kreishaus
Bus: 993

Building Access
elevator available, wheelchair-accessible
bank account:
recipients: Landkreis Emsland
bank: Emsländische Volksbank
BIC: GENODEF1LIG
IBAN: DE26266600600120050000
recipients: Landkreis Emsland
bank: Sparkasse Emsland
BIC: NOLADE21EMS
IBAN: DE39266500010000001339
recipients: Landkreis Emsland
bank: Postbank Hannover
BIC: PBNKDEFF250
IBAN: DE36250100300012132306

Ansprechpartner

Marc-André Burgdorf
responsible for:
Bernd Otten (Datenschutzbeauftragter)
Telephone: 05931 44-1605
Fax: 05931 44-391605
Room:
605
responsible for:

Landesbeauftragte für den Datenschutz Niedersachsen
Address: Prinzenstraße 5, 30159 Hannover
Timetable
Telephone: +49 511 12045-00
Fax: +49 511 12045-99

Source: Serviceportal Niedersachsen (Portalverbund des Bundes und der Länder)