Please enter a search term.
IMPORTANT: Select a location.To obtain application forms, location-specific information and contacts, select a town or zip code.

For an area outside of Lower Saxony and foreign languages, some menu items and functions are not available. Please go to the service page of the respective country.

Please specify an area.

Your selected location: Haselünne (497...)

Which place to enter?

The location is used to determine the responsible office for the selected administrative service. In most cases you can enter your place of residence to find the competent authority. However, there are also cases in which a different location must be specified. Here are some examples:

Birth certificateYou want to get married and need a birth certificate. You live in Hanover, but you were born in Celle. You must therefore state your place of birth, i.e. Celle.

Business registrationYou would like to register a business in Braunschweig. Your place of residence is Hanover. You must therefore state the location of your future business, i.e. Braunschweig.

Apply for a building permitYou would like to build a house in Wunstorf and therefore apply for a building permit. Her place of residence is currently Hanover. You must indicate the place where the house is to be built. In this case it is Wunstorf.

Site announcement


For each construction site where

  • the anticipated duration of the work exceeds 30 working days and on which more than 20 employees are working at the same time, or
  • the scope of the work is expected to exceed 500 person-days,

an advance notice containing at least the information specified in Annex I must be sent to the competent authority at least two weeks before the construction site is set up. The advance notice shall be visibly displayed on the construction site and adapted in the event of significant changes.

Which documents are required?

Mandatory information according to Annex I BaustellV:

  • Location of the construction site,
  • name and address of the client,
  • type of construction project,
  • name and address of the third party responsible in place of the client,
  • name and address of the coordinator,
  • expected starting date and duration of the work,
  • the maximum number of persons expected to be employed on the site,
  • the number of employers and contractors without employees expected to work on the site,
  • indication of the employers and contractors without employees already selected.
  • Address of the responsible third party also with telephone, fax and e-mail if necessary
  • Indication of the coordinator separately according to planning phase and execution phase, in addition to the address also with telephone, fax and e-mail if necessary

Requirements

At least two weeks before setting up a construction site where

  • the anticipated duration of the work exceeds 30 working days and on which more than 20 employees will be working at the same time, or
  • the scope of the work is expected to exceed 500 person-days.

Process flow

Pursuant to § 4 BaustellV, the client or his appointed third party must check whether one of the conditions pursuant to § 2 para. 2 BaustellV is fulfilled. If so, the advance notice must be submitted to the competent authority in good time, visibly displayed at the construction site and adapted in the event of significant changes.

What deadlines do I have to pay attention to?

The advance notice shall be submitted to the competent authority at least 2 weeks before the construction site is set up.

Appeal

Signature of the builder or third party responsible instead of the builder with place and date

What else should I know?

Rule of thumb: Advance notice is generally required if the construction activities require the deployment of at least 4 workers over a period of more than 6 months.

Section 7 (1) No. 1 BaustellV: It is a regulatory offence to intentionally or negligently fail to provide the competent authority with advance notice, or to do so correctly, completely or in good time.

When planning the execution of work on a construction project, in particular the division of work and the calculation of execution times, the general principles according to §4 of the Occupational Health and Safety Act must be observed.

The advance notice must be displayed visibly on the construction site and adapted in the event of significant changes.

Author

The text was automatically translated based on the German content.

Competent authority

One of the ten State Trade Inspectorates in Lower Saxony

Contact point

Responsible authorities


Staatliches Gewerbeaufsichtsamt Emden
Address: Brückstraße 38 , 26725 Emden
Timetable
Telephone: 04921 9217-0
Fax: 04921 9217-59
Fax: 04921 9217-58

Source: Serviceportal Niedersachsen (Portalverbund des Bundes und der Länder)