Apply for an immission control permit for the construction and operation of plants
If you want to build and operate a plant which, due to its nature or operation, is particularly likely to cause harmful environmental effects or otherwise endanger the general public or the neighborhood, to significantly disadvantage or significantly harass, you need a permit from the competent authority. This also includes stationary waste disposal facilities for the storage or treatment of waste.
Process flow
The approval procedure shall be accompanied by a written application accompanied by the drawings, explanations and other documents necessary to verify the conditions for approval. If the application is complete, it may be complete. to make the documents publicly known and then to interpret them for one month.
In simplified approval procedures or when public participation is not carried out, there is no public interpretation and no discussion date takes place. At the latest at the same time as the public announcement of the project, the approval authority shall invite the authorities to be involved to submit their opinion on the permit conditions within one month. If there are any objections, they can be discussed with you and those who raised the objections in a public appointment.
If the approval authority has identified all the circumstances relevant to the granting of a permit, a decision on the application must be taken on , usually within 7 months of the completeness of the permit application, in the simplified procedure within 3 months. The approval notice must be substantiated in writing and will be sent to you and the persons who have raised objections. The notification of the approval notice to objectors may be replaced by a public announcement.
Competent authority
In Lower Saxony, responsibility lies with the State Labour Inspectorates, the Hanover Region, the districts, independent cities or large independent cities.
Which documents are required?
Application programme ELiA - Lower Saxony Labour Inspectorate
What are the fees?
Ordinance on Fees and Expenses for Official Acts and Services (General Fees Regulations - AllGO-)
What deadlines do I have to pay attention to?
The operator shall have it approved by the competent authority before the installation and operation of the installation.
Legal basis
§ 4 Federal Immission Control Act (BImSchG)
in conjunction with § 10 of the Federal Immission Control Act (BImSchG)
Applications / forms
- Written form required: yes
- Personal appearance necessary: if necessary. yes
Appeal
Contradiction
What else should I know?
Application programme ELiA - Lower Saxony Labour Inspectorate
Author
The text was automatically translated based on the German content.
Technically approved by
Lower Saxony Ministry for the Environment, Energy, Building and Climate Protection