Authorisation to commence operation of an energy supply network in accordance with the Energy Industry Act

The commencement of operation of an energy supply network requires a permit pursuant to Section 4 (1) of the Energy Industry Act (EnWG) by the competent authority under Land law.

Who should I contact?

The responsibility lies with the Lower Saxony Ministry for the Environment, Energy, Building and Climate Protection.

This procedure can also be carried out through a "Point of Single Contact". The "Point of Single Contact" is a special service offered by municipalities and the state for service providers.

Find your Point of Single Contact

Requirements

When applying for the start of operation of the energy supply network, the applicant must demonstrate that he has the human, technical and economic capacity and reliability to ensure long-term grid operation in accordance with the provisions of the EnWG.

Which documents are required?

When applying for the start of operation of the energy supply network, the applicant must demonstrate that he has the human, technical and economic capacity and reliability to ensure long-term grid operation in accordance with the provisions of the EnWG.

What are the fees?

According to Annex 1 to § 1 paragraph 1 of the General Schedule of Fees of the State of Lower Saxony No. 27.1.1., the amount of the fees depends on the time required.

However, there is a minimum of EUR 500.00 and a maximum of EUR 5,000.

General Rules of Fees (AllGO)

What deadlines do I have to pay attention to?

Authorisation for network operation shall be obtained prior to commencement. § 4 para. 1 sentence 2 EnWG provides for a decision of the competent authority within 6 months after complete application documents are available. Accordingly, the application must be submitted in good time.

Processing duration

The competent authority shall take a decision within 6 months of the receipt of complete application documents.

§ 4 para. 1 sentence 2 Energy Industry Act (EnWG)

Appeal

Action before the competent administrative court

Technically approved by

Lower Saxony Ministry for the Environment, Energy, Building and Climate Protection

Author

List-ID 081 (whitelist; Status: 13.09.2018)

The text was automatically translated based on the German content.

Source: Serviceportal Niedersachsen (Linie6PLus)